Special Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Good News !!! PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam is now Stable and With Pass Result

PMI-RMP Practice Exam Questions and Answers

PMI Risk Management Professional (PMI-RMP) Exam

Last Update 1 month ago
Total Questions : 221

PMI Risk Management Professional (PMI-RMP) Exam is stable now with all latest exam questions are added 1 month ago. Incorporating PMI-RMP practice exam questions into your study plan is more than just a preparation strategy.

PMI-RMP exam questions often include scenarios and problem-solving exercises that mirror real-world challenges. Working through PMI-RMP dumps allows you to practice pacing yourself, ensuring that you can complete all PMI Risk Management Professional (PMI-RMP) Exam practice test within the allotted time frame.

PMI-RMP PDF

PMI-RMP PDF (Printable)
$43.75
$124.99

PMI-RMP Testing Engine

PMI-RMP PDF (Printable)
$50.75
$144.99

PMI-RMP PDF + Testing Engine

PMI-RMP PDF (Printable)
$63.7
$181.99
Question # 1

A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.

What should the risk manager of the related project have done to prevent this situation from happening?

Options:

A.  

Reformed the risk monitoring and closing process properly.

B.  

Created the project work plan and budget more accurately.

C.  

Educated the project team on budget change requests.

D.  

Communicated better with the organization's CEO.

Discussion 0
Question # 2

in a complex and critical project, a sponsor asks the risk manager to determine where the project's concentration of risks is greatest by performing a quantitative risk analysis. There are no organizational process assets (OPAs)s about the risk categories.

Which tool could the risk manager use to discover the project risk categories?

Options:

A.  

Work breakdown structure (WBS)

B.  

Affinity diagram

C.  

Monte Carlo simulation

D.  

Mind mapping

Discussion 0
Question # 3

During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?

Options:

A.  

A potential need to share the space with other machinery

B.  

A different type of equipment received before installation

C.  

A time delay during air conditioning installation activities

D.  

A quality nonconformance issue raised during the inspection

Discussion 0
Question # 4

An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?

Options:

A.  

Update the risk register

B.  

Meet with the project's stakeholders

C.  

Revise the risk management plan

D.  

Ensure sufficient resources are available

Discussion 0
Question # 5

A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because the end date is longer than expected.

What should the risk manager do first?

Options:

A.  

Remove the activity padding.

B.  

Review the risk response plan.

C.  

Update the risk contingency plan.

D.  

Update the schedule constraints.

 

Discussion 0
Question # 6

A project is in the execution phase and involves large volumes of supplies. The project is the last phase of a 10-year initiative. The project sponsor asks the project manager to provide the performance report for the whole initiative.

Which analysis should the risk manager do to provide the project manager with the performance report?

Options:

A.  

Time Series Analysis

B.  

Regression Analysis

C.  

Variance Analysis

D.  

Monte Carlo Analysis

 

Discussion 0
Question # 7

A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.

What should the project manager do next to avoid similar risks?

Options:

A.  

Add contingencies to other tasks to mitigate similar risks.

B.  

Reassess risks with a new assumptions and constraints analysis.

C.  

Review the risk response plan looking for lessons learned.

D.  

Log the event in the issue log and update the project management plan.

Discussion 0
Question # 8

A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.

Who should the project manager hold accountable for missing the risks?

Options:

A.  

The audit team

B.  

The risk manager

C.  

The risk owners

D.  

The discipline engineers

Discussion 0
Question # 9

A project team is presenting a delivery plan to a client. Some of the client's experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.

What should the risk manager do first?

Options:

A.  

Review and update the project quality management plan.

B.  

Conduct a risk assessment process for the critical stage.

C.  

Create a more detailed work breakdown structure (WBS).

D.  

Add additional time to the delivery plan to cover issues.

 

 

Discussion 0
Question # 10

During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?

Options:

A.  

Strengths, weakness, opportunities, and threats (SWOT) analysis

B.  

Delphi technique

C.  

Decision tree analysis

D.  

Probability impact matrix

Discussion 0
Get PMI-RMP dumps and pass your exam in 24 hours!

Free Exams Sample Questions