PMI-001 Practice Exam Questions and Answers

Project Management Professional v5

Last Update 2 days ago
Total Questions : 918

Project Management Professional v5 is stable now with all latest exam questions are added 2 days ago. Incorporating PMI-001 practice exam questions into your study plan is more than just a preparation strategy.

PMI-001 exam questions often include scenarios and problem-solving exercises that mirror real-world challenges. Working through PMI-001 dumps allows you to practice pacing yourself, ensuring that you can complete all Project Management Professional v5 practice test within the allotted time frame.

PMI-001 PDF

PMI-001 PDF (Printable)
$43.75
$124.99

PMI-001 Testing Engine

PMI-001 PDF (Printable)
$50.75
$144.99

PMI-001 PDF + Testing Engine

PMI-001 PDF (Printable)
$63.7
$181.99
Question # 1

Which of the following are placed at selected points in the work breakdown structure (WBS) for performance measurement?

Options:

A.  

Control accounts

B.  

Milestones

C.  

Management points

D.  

Measurement points

Discussion 0
Question # 2

Which quality planning tools and techniques are used to visually identify logical groupings based on natural relationships?

Options:

A.  

Force field diagrams

B.  

Cause-and-effect diagrams

C.  

Affinity diagrams

D.  

Nominal group techniques

Discussion 0
Question # 3

Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

Options:

A.  

Project Integration Management

B.  

Project Communications Management

C.  

Project Information Management System (PIMS)

D.  

Project Scope Management

Discussion 0
Question # 4

Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?

Options:

A.  

Acquisition

B.  

Negotiation

C.  

Virtual team

D.  

Pre-assignment

Discussion 0
Question # 5

The following is a network diagram for a project.

Question # 5

The free float for Activity H is how many days?

Options:

A.  

4

B.  

5

C.  

10

D.  

11

Discussion 0
Question # 6

Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

Options:

A.  

Collect Requirements

B.  

Direct and Manage Project Execution

C.  

Monitor and Control Project Work

D.  

Develop Project Management Plan

Discussion 0
Question # 7

During which process group is the quality policy determined?

Options:

A.  

Initiating

B.  

Executing

C.  

Planning

D.  

Controlling

Discussion 0
Question # 8

Requirements documentation will typically contain at least:

Options:

A.  

Stakeholder requirements, staffing requirements, and transition requirements.

B.  

Business requirements, the stakeholder register, and functional requirements.

C.  

Stakeholder impact, budget requirements, and communications requirements.

D.  

Business objectives, stakeholder impact, and functional requirements.

Discussion 0
Question # 9

Progressively elaborating high-level information into detailed plans is performed by the:

Options:

A.  

project management office

B.  

portfolio manager

C.  

program manager

D.  

project manager

Discussion 0
Question # 10

Which tool or technique is required in order to determine the project budget?

Options:

A.  

Cost of quality

B.  

Historical relationships

C.  

Project management software

D.  

Forecasting

Discussion 0