C_TS422_2023 Practice Exam Questions and Answers

SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing

Last Update 19 hours ago
Total Questions : 80

SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing is stable now with all latest exam questions are added 19 hours ago. Incorporating C_TS422_2023 practice exam questions into your study plan is more than just a preparation strategy.

C_TS422_2023 exam questions often include scenarios and problem-solving exercises that mirror real-world challenges. Working through C_TS422_2023 dumps allows you to practice pacing yourself, ensuring that you can complete all SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing practice test within the allotted time frame.

C_TS422_2023 PDF

C_TS422_2023 PDF (Printable)
$48
$119.99

C_TS422_2023 Testing Engine

C_TS422_2023 PDF (Printable)
$56
$139.99

C_TS422_2023 PDF + Testing Engine

C_TS422_2023 PDF (Printable)
$70.8
$176.99
Question # 1

What are the options if the Dispatched operation status is set for a production order operation?

Note: There are 2 correct answers to this question.

Options:

A.  

You can reschedule the operation using finite scheduling in a planning table.

B.  

You can reschedule the operation in the Manage Production Operations app.

C.  

You can reschedule the operation using infinite scheduling in a planning table

D.  

You can reschedule the operation using midpoint scheduling in a planning table.

Discussion 0
Question # 2

Which information is required when you create a product master in SAP S/4HANA?

Note: There are 2 correct answers to this question.

Options:

A.  

Product type

B.  

Selection screen for views

C.  

Selection screen for plants

D.  

Base unit of measure

Discussion 0
Question # 3

How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 Correct answers to this question.

Options:

A.  

Increase the capacity supply in a time-phased interval.

B.  

Determine a time period with available capacity on the planning board.

C.  

Execute an infinite production planning run for the critical resources.

D.  

Reduce the planning Window.

E.  

Form optimum sequence to reduce setup times.

Discussion 0
Question # 4

You can you use capacity availability checks for production orders, which settings have to be made for this?

Note: There are 2 Correct answers to this question?

Options:

A.  

The relevant for finite scheduling indicator must be set.

B.  

A checking rule must be assigned to the work centers

C.  

An overall profile must be assigned in the checking control

D.  

The scope of check must be defined in customizing.

Discussion 0
Question # 5

You use planning strategy Finite Scheduling with Reverse and want to allow scheduling the past. How can you parameterize this in the strategy profile?

Options:

A.  

Specify a negative planning horizon.

B.  

Specify a positive planning horizon.

C.  

Specify a positive offset time.

D.  

Specify a negative offset time.

Discussion 0
Question # 6

Advanced Planning uses master data and transaction data from SAP S/4HANA In which data objects can you set the Advanced Planning flag?

Note: There are 2 correct answers to this question.

Options:

A.  

Work Center

B.  

Production Version

C.  

Material

D.  

plant

Discussion 0
Question # 7

You are trying to create a production order and NO valid production version can be selected. What could be the reasons?

Note: There are 2 correct answers to this question.

Options:

A.  

NO bills of material (BOMs) are assigned to the production versions.

B.  

All production versions for the material are locked.

C.  

The order lot size is NOT within the validity range of a production version.

D.  

NO production lines are assigned to the production versions..

Discussion 0
Question # 8

Which of the following questions do you have to answer before you start creating a bill of material (BOM)?

Options:

A.  

Is the material type allowed in the BOM?

B.  

Which base unit of measure does the material have?

C.  

What status does the BOM have?

D.  

In which storage location is the BOM required?

Discussion 0
Question # 9

What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?

Options:

A.  

The planned order is converted to a production order.

B.  

The planned order's component availability is checked.

C.  

The planned order generates capacity requirements

D.  

The planned order's components are copied to the picking list.

Discussion 0
Question # 10

Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA?

Note: There are 2 correct answers to this question.

Options:

A.  

Order (pool) chart

B.  

Capacity requirements chart

C.  

Work center capacities chart

D.  

Orders (dispatched) chart

Discussion 0