CDCS Practice Exam Questions and Answers

EXIN EPI Certified Data Centre Specialist

Last Update 2 days ago
Total Questions : 60

EXIN EPI Certified Data Centre Specialist is stable now with all latest exam questions are added 2 days ago. Incorporating CDCS practice exam questions into your study plan is more than just a preparation strategy.

CDCS exam questions often include scenarios and problem-solving exercises that mirror real-world challenges. Working through CDCS dumps allows you to practice pacing yourself, ensuring that you can complete all EXIN EPI Certified Data Centre Specialist practice test within the allotted time frame.

CDCS PDF

CDCS PDF (Printable)
$43.75
$124.99

CDCS Testing Engine

CDCS PDF (Printable)
$50.75
$144.99

CDCS PDF + Testing Engine

CDCS PDF (Printable)
$63.7
$181.99
Question # 1

Smoke sensors need to be tested to ensure that they pick up a potential fire in the data center.

What should you recommend?

Options:

A.  

Test the sensors by injecting smoke or simulated smoke directly into the sensor

B.  

Press the self-test button on each sensor in the data center

C.  

Inject smoke at the floor level

D.  

Test the sensors according to the vendor specification

Discussion 0
Question # 2

What indicates the breaking capacity of a fuse or breaker?

Options:

A.  

Mechanical strength of the casing of a fuse or breaker.

B.  

The maximum voltage, in case of an electrical surge, that the fuse or breaker can handle without being destroyed or causing an electric damaging arc.

C.  

The current at which the device will trip.

D.  

The current that a fuse or breaker is able to interrupt without being destroyed or causing an electric damaging arc.

Discussion 0
Question # 3

An MCB needs to be installed in the PDU of an air-conditioner unit.

Which breaking curve should you select?

Options:

A.  

D-Curve

B.  

C-Curve

C.  

B-Curve

D.  

A-Curve

Discussion 0
Question # 4

What is the main disadvantage of using a ToR (Top of Rack) design?

Options:

A.  

A single ToR (Top of Rack) switch is more expensive than an EoR (End of Row) switch.

B.  

You need a separate rack to install all your ToR (Top of Rack) switches.

C.  

There will be more switches to manage.

D.  

A ToR (Top of Rack) switch has only optical interfaces.

Discussion 0
Question # 5

The 'maximum exposed area' of the fire-rated glass is defined by the supplier as 3 sqm/32 sqft. The window area is 4 sqm/43 sqft.

What would be the best option?

Options:

A.  

Do not use fire-rated glass due to the size limit and replace it with normal glass.

B.  

Split the window in two equal parts using an aluminum frame.

C.  

Split the window into parts smaller than specified as the maximum exposed area and ensure fire-rated frames are used.

D.  

Split the window in two equal parts fitted together with transparent silicon glue.

Discussion 0
Question # 6

In order to save energy, you are going to install an automated system to switch off lights. What should be taken into consideration when installing such a system?

Options:

A.  

Security guards should perform regular inspections verifying the system works.

B.  

The system should not be based on motion detection as the lights might suddenly switch off while staff is still at work.

C.  

It is not advisable to use such a system since it will reduce the lifetime of LED lighting.

D.  

At all times, the levels should allow for security cameras to function properly.

Discussion 0
Question # 7

You are installing new copper cabling.

What is the advantage or disadvantage of choosing pre-terminated category 6 or 6A cabling?

Options:

A.  

Pre-terminated cabling is already factory tested and saves installation time.

B.  

There is no advantage as most new copper cabling network designs are based on category 3 or 5E for horizontal cabling.

C.  

Pre-terminated cabling has a higher fire rating.

D.  

Pre-terminated cabling makes ordering of the copper cables more complex, as you need to know in advance on which side the male or female connector needs to be located.

Discussion 0
Question # 8

Three data centers are benchmarked on facilities energy efficiency.

Data center A has achieved a PUE of 2.45.

Data center B has achieved a PUE of 1.20.

Data center C has achieved a PUE of 1.90.

Which of the data centers is operating at the highest facility efficiency?

Options:

A.  

PUE does not indicate efficiency

B.  

Data center A

C.  

Data center B

D.  

Data center C

Discussion 0
Question # 9

A computer room with a raised floor has been designed with racks in a hot/cold aisle setup.

What should you recommend for the placement of down-flow air conditioners?

Options:

A.  

Air conditioners perpendicular to (at the end of the row of) the Cold-Aisle

B.  

Air conditioners perpendicular to (at the end of the row of) the Hot-Aisle

C.  

Air conditioners should always be placed at both sides of each row of racks

D.  

Air conditioner placement has no influence on cooling effectiveness and efficiency. Hence, they can be placed at any convenient location.

Discussion 0
Question # 10

You need to determine the strategy for the cooling audit. All the servers are based on a front-to-rear (F-R) airflow design.

Which location for the temperature/humidity measurement should you recommend for the audit?

Options:

A.  

At the back/rear of the server at 50 mm/2 inch

B.  

At 1.5 meters/5 feet above the floor in the middle of the cold aisle

C.  

At the front/intake of the server at 50 mm/2 inch

D.  

At 1.5 meters/5 feet above the floor in the middle of the hot aisle

Discussion 0