Agile Project Management (AgilePM) Practitioner Exam
Last Update 23 hours ago
Total Questions : 78
Agile Project Management (AgilePM) Practitioner Exam is stable now with all latest exam questions are added 23 hours ago. Incorporating AgilePM-Practitioner practice exam questions into your study plan is more than just a preparation strategy.
AgilePM-Practitioner exam questions often include scenarios and problem-solving exercises that mirror real-world challenges. Working through AgilePM-Practitioner dumps allows you to practice pacing yourself, ensuring that you can complete all Agile Project Management (AgilePM) Practitioner Exam practice test within the allotted time frame.
During Refinement in Timebox B, a Review Session was scheduled for the Business Visionary to review the products completed during this Timebox, and to agree what
needed to be done before these would be acceptable.
Is this an appropriate application of Agile Project Management for this project?
Who is responsible for approving that the change in priority of the requirement for a secondary exit from the upstairs of the building accurately reflects the scope of the
project in the Prioritised Requirements List?
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The requirement to 'install a heat reclamation system' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.
Is this an appropriate action related to acceptance criteria?
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.
Is this an appropriate action related to acceptance criteria?
Using the Project Scenario answer the following question about the technical quality of the solution to be delivered. An assessment of the maintenance requirement for the new reservation system was made during Feasibility.
Column 1 describes a list of different types of hotel reservation systems considered. Column 2 lists the three DSDM maintainability objectives. For each description in Column 1, select from Column 2 the maintainability objective it would support.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1. Off-the-shelf software with ready-to-use templates that will need to be customised to fully
meet Hoy Hall requirements, after deployment.
2. Developing a fully functioning in-house system, developed and hosted by Architecture
Angels IT Operations team.
3. All-in-one web-based reservation and accommodation management system built to Hoy Hall's
specification.
4. All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group,
until a suitable system can be implemented at the site.
5. A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.
Column 2
Maintainability is a required attribute of the initial delivered solution
Deliver first, re-engineer later
Short-term, tactical solution
The Business Sponsor threatened to stop funding if there was no evidence of tangible progress. To reduce this risk, the Business Sponsor was invited to several walk-
rounds of the new bedroom and en-suite bathroom facilities throughout the project.
Is this an appropriate application of Agile Project Management for this project?
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
During Solution Development Timebox A, a new Health and Safety requirement arises: the front door is required to have wheelchair access. This is a legal requirement and is a Must Have before any staff or general public access can be allowed. The Solution Development Team will work with the Local Planning Authority Officer, the specialist who identified the requirement, to identify further acceptance criteria for Solution Development Timebox
A.
Is this an appropriate action related to acceptance criteria?
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility.
Remember to limit your answers to the number of selections requested in each question.
Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?
Which 2 actions should the Workshop Facilitator take when preparing for the workshop?
Answer the following questions about the tracking and control activities carried out within the project.
Decide whether each activity has been applied appropriately and select the response that supports your decision.
During Foundations, the key stakeholders had very different views about the content and prioritisation for the high-level requirements. As a result, the Project Manager
organized a Facilitated Workshop with the project team to discuss and agree the requirements.
Is this an appropriate application of Agile Project Management for this project?
TESTED 23 Nov 2024
Hi this is Romona Kearns from Holland and I would like to tell you that I passed my exam with the use of exams4sure dumps. I got same questions in my exam that I prepared from your test engine software. I will recommend your site to all my friends for sure.
Our all material is important and it will be handy for you. If you have short time for exam so, we are sure with the use of it you will pass it easily with good marks. If you will not pass so, you could feel free to claim your refund. We will give 100% money back guarantee if our customers will not satisfy with our products.